THE Metropolitan Manila Development Authority (MMDA) has proposed the construction of rainwater impounding facilities inside Camp Aguinaldo to ease recurring flooding on EDSA, with the proposed design released on Wednesday, Aug. 27.

The plan requires detention ponds that will temporarily store excess rainwater during downpours and gradually release it into the EDSA drainage system, leading to the Makiling Creek., This news data comes from:http://www.gyglfs.com
As proposed, the project will be implemented in three phases, covering 182 hectares and involving a golf course near Gate 2, another near Gates 3 and 4, and an open space near Gate 6.
MMDA proposes rainwater facilities in Camp Aguinaldo to mitigate EDSA flooding
For the first phase near Gate 2, the detention pond has a 361-meter perimeter, a 4,650-square-meter area, an 8-meter depth, and a 37,200-cubic-meter capacity, designed for a 25-year return period (15.6 mm per hour over 24 hours), exceeding the needed 36,945 cubic meters.
MMDA proposes rainwater facilities in Camp Aguinaldo to mitigate EDSA flooding
MMDA’s schematic shows that under normal weather, the water bypasses the pond and flows through the lagoon to EDSA.
During heavy rain, floodgates divert water flow into the pond; after rain, pumps discharge stored water slowly into EDSA toward the Makiling Creek.
The scope of works covers the impounding area, operations and powerhouse, drainage and electromechanical works, and landscaping and golf course restoration, with a treatment facility under consideration.
Officials said operations and maintenance arrangements, and a memorandum of agreement, are still under discussion.
- Most Filipinos distrust China, see it as biggest threat — OCTA survey
- SC acquits suspect in 2012 killing of Dutch aid worker over doubtful testimonies
- Marcos sacks PNP Chief Torre, saying it was 'difficult but necessary'
- One in four people lack access to safe drinking water – UN
- Wildfires producing 'witches' brew' of air pollution – UN
- No winner in Ultra, Megalotto draws for Sept 5
- Marcos orders full budget review for DPWH amid ghost projects scandal
- Former PNP chief Torre III offered new government post
- Palace suspends govt work, classes in several areas due to bad weather
- 2 policemen placed under preventive custody for allegedly molesting a female colleague in Marikina